Creating Equations, Polynomials, and Quadratic Functions — Test

Question 3 • CMS 2026-2027 NC Math 2 CREDIT RECOVERY

A landscaper estimates that a set of plants can be installed in 6 hours by 12 workers. The landscaper wants to finish a set of plants in 4 hours. Assuming that the variables are inversely related, how many workers should the landscaper bring to the job?

Answer
A
8
B
14
C
18
D
10

Explanation

For an inverse relationship, the number of workers multiplied by the time stays constant. The job requires 12 × 6 = 72 worker-hours, so finishing in 4 hours requires 72 ÷ 4 = 18 workers. The landscaper should bring 18 workers, choice C.