A project can be completed by 5 workers in 24 days. How many workers are needed to finish the project in 15 days? The time to complete a project is inversely proportional to number of people who are doing the project.

Answer
A
10
B
12
C
6
D
8

Explanation

Because the time is inversely proportional to the number of workers, the total amount of work stays constant. The project requires 5 × 24 = 120 worker-days, so finishing it in 15 days takes 120 ÷ 15 = 8 workers. The correct choice is 8 workers.