Question 11 • Intro Engineering & Product Dev A
Correct Answer:
Three important constraints are: 1. **Existing server compatibility and capacity:** The new POS terminals must work with the current server’s hardware, operating system, software, and available capacity. Replacing or substantially upgrading the server may be outside the project’s scope. 2. **Network access and security:** The terminals depend on a reliable connection to the remote server. Network bandwidth, outages, access permissions, encryption, and security policies can limit how and when the terminals connect. 3. **Budget and implementation schedule:** The project must fit within the approved funding and deadline. Installation, configuration, testing, and staff training must be scheduled around business operations and any permitted service downtime.