Question 4 • Intro Engineering & Product Dev A

Which option identifies the section of a project charter represented in the following scenario?Updated POS terminals will be available to the following five departments by July 31, 2015.

Answer
A
project constraints
B
project deliverables
C
project requirements
D
project assumptions

Explanation

The statement identifies the project’s output: updated POS terminals made available to five departments. Project deliverables are the products or results a project is expected to produce; the July 31 date specifies when they should be available. Therefore, this is the project deliverables section.