Unit Test — Unit test

Question 3 • WSFCS Math 2 CR

A landscaper estimates that a set of plants can be installed in 6 hours by 12 workers. The landscaper wants to finish a set of plants in 4 hours. Assuming that the variables are inversely related, how many workers should the landscaper bring to the job?

Answer
A
8
B
10
C
14
D
18

Explanation

With an inverse relationship, the number of workers multiplied by the hours stays constant. The job requires 12 × 6 = 72 worker-hours, so finishing in 4 hours requires 72 ÷ 4 = 18 workers. Therefore, the landscaper should bring 18 workers.

AI-written and checked against the verified answer.